Sourcing timber sleepers for the Kowloon Canton Railway

While reading through historical annual reports for the Kowloon Canton Railway, I came across an interesting piece on the troubles they encountered sourcing suitable timber railway sleepers that could withstand Hong Kong’s tropical conditions.


PA Images photo

The 1948-49 Kowloon Canton Railway annual report, page 16 is where I first read of their timber sourcing issues:

New Sleepers

During the year, the following quantities of hardwood sleepers were purchased:-

2,369 Siamese Hardwood Sleepers
301 Siamese Hardwood Crossing Timbers
4,000 Borneo Hardwood Sleepers

A local trading company failed to carry out the contract for the supply of 1,000 bridge and crossing timbers owing to the sudden imposition of a 10% export tax by the Siamese Government.

As well as the various types of timber previously used.

Kempas Sleepers. The majority of the timber sleepers removed from the track after the war (i.e. 1946 to 1948) were Singapore Kempas sleepers obtained as an experiment in 1938. These sleepers were creosote-treated. They started to rot from the core, and this was not easily detected from the outside until they were in an advanced state of decay.

Australian Sleepers. With the exception of the 2,000 pieces put in the track during Autumn 1946, all Australian hard- wood sleepers found in this Railway are over 15 years old and are still serviceable. No hardwood sleepers in these latitudes so far handled can compare with Australian Eucalypts.

Siamese Sleepers. Some Siamese sleepers were purchased six months ago, but it is yet too early to comment as to the probability of their useful life.

Borneo sleepers were received in the Colony in January 1949, and were first put in the track in April. Here again, it is too early to comment.

We are indebted to the Forestry Officer for the advice and assistance afforded to the Department on sample timbers, and the inspection of sleepers imported for Railway use.

As well as the experimental concrete railway sleepers that were developed in the 1920s.

Up to 31 March 1949 there were:

19,935 concrete sleepers on the Main Line
8,565 concrete sleepers on sidings
3 ,785 concrete sleepers lying in yard (not on track)

32,285 concrete sleepers against an approximate total of 35,000 manufactured between 1920 and 1934.

It is worthy of note that after an average period of 22 years, 90% of Baker’s concrete sleepers are still in existence. Unfortunately it was necessary, however, when replacing 85-lb. rails with 95-lb., to remove the concrete sleepers from the curves in the Main Line due to the wider bottom of the new rail and the insufficient spread allowed by the concrete sleepers. The concrete sleepers thus removed were re-used in other places.

Issues sourcing timber sleepers continued through 1949-50.

A local contractor failed to fulfil the contract for the supply of 12,100 hardwood sleepers. Only 1,479 were delivered.

The successive non-fulfilment of contract for the supply of hardwood sleepers by local contractors in 1948/49 and 1949/50 has resulted in a shortage of 11,621 sleepers which means a delay in the renewal of 4 miles of tracks and 35 sets of points and crossings.

By 1950-51 the supply issues now related to the cresote used to protect timber sleepers from rotting.

In all, 22,727 Mai Yang sleepers and 3,322 bridge and crossing timbers were purchased from the Forest Industry Organization, Bangkok, through the Siam Rice Agency Ltd., acting as shipping agents.

The Forestry Officer, Hong Kong, recommended that the Mai Yang sleepers should be treated with 50% creosote and 50% diesel oil mixture by the open tank process, and therefore a pre-war plant for treating Kempas sleepers was reconditioned and used for this purpose. Work was started on 3.10.1950.

Owing to the intermittent short-supply of creosote from the United Kingdom due to shortage of drums, only 2,874 sleepers were treated in the first six months. An arrangement with a local firm of repute would have resulted in a regular supply admittedly at higher cost, but the Chairman of the Tender Board advised purchase through the Crown Agents. The final cost of the cheaper creosote will, in due course, be reflected in the earlier replacement of non-creosoted sleepers which are very difficult to obtain.

Some 1,121 very rotten timber sleepers lying alongside the track in the New Territories were sold as they lay: 5,500 were given to the Social Welfare Office for the use of a refugee camp, and 1,521 were brought back to Kowloon and sold to railway staff as firewood.

A shortage of hardwood sleepers delayed the main line re-railing program in 1951-52, with the work not completed until February 1953.

From that point it is believed that spot replacement of timber sleepers continued until the modernisation of the Kowloon Canton Railway through the 1970s, when the line was relaid in even heavier rail – UIC54 profile at 54 kg/m, or 109-lb. in the old measures – laid on modern precast concrete sleepers.

Concrete sleepers on the East Rail line

Footnote: the modern era

Timber railway sleepers are still used on the MTR system today, but predominately beneath points and crossings, thanks to the flexibility they provide for these pieces of complicated trackwork.

Timber sleepers trackside at Hung Hom

But timber sleepers can also be occasionally be found on tracks elsewhere – presumably due to clearance issues.

Yes, the MTR uses timber sleepers!

But since 2008 the MTR have made moves to replace them with “synthetic sleepers”.

There were originally about 10 000 “timber sleepers” on the East Rail Line (EAL). They are also used on relatively longer sections of Tung Chung Line and Airport Express Line.

Due to the ageing of and difficulties in procuring “timber sleepers”, the MTRCL has gradually replaced “timber sleepers” with sleepers made of synthetic materials since 2008 and will replace sleepers in the light of their actual conditions and ages. In terms of railway applications, there is no difference between the mechanical properties of synthetic sleepers and timber sleepers. The mechanical properties of both sleepers are in compliance with the Japanese Industrial Standard (Standard JIS E 1203:2007).

Generally speaking, “synthetic sleepers” have a longer lifecycle than “timber sleepers” and are able to improve the overall track reliability. Thus, “synthetic sleepers” are widely used in railway systems around the world.

The MTRCL started to implement the plan for replacing worn out “timber sleepers” on EAL in 2010. As at August 2019, 4,000 timber sleepers have been replaced by synthetic sleepers.

Since then the MTRCL has replaced over 2,600 “timber sleepers” to give extra track reliability. The remaining “timber sleepers” with better conditions will also be replaced by the end of 2021. By then, the replacement of all “timber sleepers” on EAL will be completed.

The “synthetic” sleepers in question are FFU synthetic wood sleepers manufactured by the Japanese company Sekisui Railway Technology.


Sekisui Railway Technology photo

The technology having been proven in Japan for decades.

FFU is produced by compressing single strands of glass fibre with polyurethane foam using a high-pressure extraction press. The manufacturing process is initiated by mixing the base materials polyole and isocyanide with several additives, and after compounding and extrusion, the raw mixture is reinforced with long glass fibres. Foaming and curing then takes place before the finished product is cut to a standard length of 12m for further processing and sizing to any length determined by customers.

One of the major benefits of the sleepers is their longevity. This was recently demonstrated in a study conducted by Japan’s Railway Technical Research Institute (RTRI) on behalf of Sekisui of FFU synthetic short sleepers and FFU synthetic bridge sleepers which have been in service in Japan for the last 30 years.

The survey results show that after 15, 20, 25, and 30 years in service the short sleepers exhibited no cracks and warping, no changes in the colour of the surface layer, and no loose screw spikes, and overall were in good fixed condition. Furthermore, the sleeper plates were in good fastened condition, while no peeling or cracks, or loose sleepers were found during observations of the bonded portions from the ditch side.

But were to blame in a September 2019 derailment on the MTR East Rail line at Hung Hom.

Thanks to the synthetic sleepers behaving differently under load than timber sleepers.

The Panel concluded that the derailment was caused by the dynamic track gauge widening beyond a critical level at turnout P5116. The investigation found that, in the early hours of 4 August 2019, the EAL Track Maintenance Team replaced two worn out timber sleepers with new synthetic sleepers to correct the track gauge.

Due to the special combination of rail alignment at a sharp curve, high traffic intensity and the difference in stiffness between the new synthetic sleepers and neighbouring sleepers in this particular location, this arrangement had an unintended consequence in that the two synthetic sleepers created a localised hard spot in the rail support system. This hard spot resulted in most of the sideways loading from the trains passing through this curved section being exerted onto the rail fastening of the two newly replaced synthetic sleepers, which accelerated the fastening’s deterioration.

Three of the fixing screws failed as a result, which allowed one of the rails to move sideways, leading to an increase in the gap between the two rails or “dynamic track gauge widening beyond a critical level” and train wheels hitting the check rail. This in turn led to the derailment.

So it seems nothing is ever that simple.

Posted in Transport | Tagged , , , , , , , , , , | Leave a comment

Hong Kong experiments in concrete railway sleepers

Today concrete railway sleepers are a common sight on railways around the world, including Hong Kong, but recently I discovered that the Kowloon Canton Railway was involved in their early development.

Concrete sleepers on the East Rail line

Down the rabbit hole

Concrete sleepers are mentioned in the Institution of Civil Engineers’ obituary for Robert Baker OBE, former Chief Engineer for the Kowloon Canton Railway.

After three years’ training in the manufacture of instruments he was articled for three years to Sir Robert Elliott-Cooper, and then embarked on a varied career of railway engineering, serving in England, Greece, Malaya, and China from 1911 until his retirement in 1934. He was concerned mainly with the administration and maintenance of the Kowloon-Canton Railway in Hong Kong, filling the post of Chief Engineer from 1927 onwards, combining that post with Manager. During that time he did some pioneer work in the development of reinforced concrete sleepers.

His experiments commenced in the early 1920s, as this article from the Singapore Free Press and Mercantile Advertiser dated 26 January 1922 describes.

A Hongkong resident, Mr. R. Baker, of the Kowloon-Canton Railway, has recently patented at home his invention of a new kind of concrete railway sleeper, experiments with which have so far proved the idea to be a great success. A company called the Timeproof Ferro-Concrete Railway Sleeper Co., with its offices at Westminster, has been formed to control the Manufacturing rights.

With the establishment of the company mentioned on page 85 of the 20 January 1922 issue of ‘The Electrician’.

Timeproof Ferro-Concrete Railway Sleeper Company, Ltd. (178 965), 2, Dean’s-yard, The Sanctuary. Westminster, S.W. Registered Jan. 10. To acquire from Robert Baker the benefit of an invention for improvements in railway and tramway sleepers, and turn same to account. Nominal capital, £900 in” 750 ordinary shares of £1 each and 3 000 founders’ shares of Is. each. Directors”: R. Baker, D. Macdonald, W. Daniel, and E. A. Kite. Qualification of directors, one share. Remuneration of directors. £50 each. Chairman, £75.

And finally after a lot of digging, I finally found an in depth article on the new invention in the 5 January 1922 edition of the Hong Kong Telegraph.

Hongkong Resident’s Invention
A New Railway Sleeper

A Hongkong resident, Mr. R Baker, of the Kowloon-Canton Railway, has invented a new kind of concrete railway sleeper, experiments with which have so far proved the idea to be a great success. Mr. Baker went Home a short time ago to patent the invention. A number of big people in the railway world be came interested, and a Company to control the manufacturing rights was formed. It is called the Timeproof Ferro-Concrete Railway Sleeper Co., and the offices of the Company are at Westminster.

The idea of a concrete sleeper is by no means a new one, Italy had about a hundred miles of rail way line laid on concrete sleepers in 1915, but as little or nothing has been heard of the scheme for several years it is to be concluded that the idea was not a success. Mr. Baker’s sleepers, however, are different from any of the previous styles. There are some three or four hundred laid near Shatin and these have been such a success that their inventor considered the idea worth patenting.

Mr. Baker has been working on the invention for several years and has experimented with several types before selecting the one which he has now had patented. It was in Sir Henry May’s time, in fact, that he first started his experiments. It is understood, that the present Governor looks upon the invention very favourably and it is, to a great extent due to Sir Edward Stubbs that the idea in being seriously taken up.

The new sleeper is quite different in appearance to the old wooden sleepers to which we are accustomed. It is of cruciform section in the middle and fairly narrow. It gets wider at the rail seats and tapers at the ends. It is of concrete, in the centre of which are a number of steel bars. It has several advantages over the old-fashioned type of wooden sleeper and it is claimed that it has also many advantages over concrete and other sleepers with which experiments have been made in white ant countries the life of a wooden sleepers not long and another great enemy of the wooden kind is dry rot. The sleepers on the Kowloon-Canton Railway come from New South Wales. They cost about fifteen shillings each at the present time, they require a great deal of attention and their life is about twelve years.

The Baker sleepers will work out st about $10 each, but as they will not be liable to attack by white ants or dry rot it will not – be necessary to treat them with kerosene oil to preserve them, which will be a great saving, and the inventor sees no reason why is they should not last half a century or more.

One great advantage with the Baker sleeper is that it does not require so much ballast as other kinds, and one thing it will help to prevent is people walking between the metals. The old wooden sleepers are placed at such a convenient distances apart that coolies often walk between the metals, stepping from sleeper to sleeper. Many have met their death in this way, but sa the new concrete sleeper is sharp and not flat on the top, walking on them will not be possible and this undesirable practice will have to cease.

The new sleeper is receiving considerable attention in the railway world. The Great Western Railway at Home is experimenting with the new Baker sleeper’s and railways in Jamaica and Tanganyika are making inquiries.

It will probably be some time before all the Kowloon-Canton Railway is laid on these sleepers, owing to the extra cost. The British section contains some 60,000 sleepers and taking the life of the average at ten years (it might be a little more than that), that means replacing about six thousand sleepers a year. The concrete sleepers cost nearly double the wooden kind, however, and it will probably not be possible to replace all wooden sleepers with concrete ones, at present, but Mr. Baker says he hopes to be able to lay about a thousand a year.

Specimens of “ant-proof railway sleeper” were exhibited in the Hong Kong Section of the European Exporters’ Rooms at the 1922 British Empire Exhibition, but it appears that the Timeproof Ferro-Concrete Railway Sleeper Co. was not a success – the London Gazette dated 5 September 1939 advising that the company would be struck off the register and dissolved, which occurred on 8 December 1939.

So what did Baker’s concrete sleepers look like?

It was lucky that Robert Baker patented his concrete sleeper design, as that should mean detailed documentation of them should still exist – with a quick search on Google Patents bringing up a United Kingdom patent application titled ‘Improvements in railway and tramway sleepers‘ by an R Baker, dated October 1920, and an Australian one with the same and author dated March 1922.

Unfortunate both lacked the full text of the application, so I headed over to the IP Australia website, found the relevant patent application, and lo and behold – the full text!


Australian parent application 1922005839

Describing the invention as:

I, Robert Baker, c/o The Kowloon-Canton Railway, Hong Kong, China, Engineer, hereby declare this invention and the manner in which it is to be performed, to be fully described and ascertained in and by the following statement:-

This invention relates to reinforced concrete sleepers for railways or tramways.

According to this invention the reinforced concrete sleeper is of cruciform section at the centre and rectangular section at the rail seats. Recesses are made in the upper surface of the sleeper to form seats for hard wood or composition shock absorbing blocks upon which the rails are supported; the recesses are cast at an angle with the upper surface of the sleeper to correspond with the
required inclination given to the rail and at the same time allowing blocks of parallel or rectangular section to be used.

Preferably the ends of the sleeper are tapered at the sides and on the upper surface, and have a step underneath either side adapted to grip the ballast and assist. in preventing lateral creep or buckling of the track.

Preferably the sleeper is provided with eight reinforcing bars, two bars being located in each web of the cruciform at the centre. Six of the bars are carried through the lower portions of the sleeper under the rail and two in the upper portion whilst two additional bars may be introduced at either end which pass through the upper portions.

Along with a diagram of the sleeper design.


Australian parent application 1922005839

So how did they fare on the Kowloon Canton Railway?

Unfortunately the Hong Kong Public Libraries digitised archive of Kowloon Canton Railway annual reports only goes back to 1946, but the Hong Kong Telegraph dated 29 June 1929 offers a short summary of that year’s KCR annual report.

5,070 reinforced concrete sleepers were made departmentally; the cost of manufacture including supervision and all charges, was very much lower than previous contract prices.

2,320 concrete sleepers, 431 wooden sleepers, and 73 crossing and bridge timbers wore required to replace worn out timbers in the track.

And the website of David M. Webb has a copy of the 1934 KCR annual report, which happened to be a pivotal point in their use of concrete railway sleepers.

The manufacture of reinforced concrete sleepers ceased on the 1st August, experience having demonstrated the unsuitability of sleepers of this type.

At the end of the year, 69.6% of the sleepers in the main line were concrete.

Permanent Way renewals were as follows:-

– 5,000 “Timeproof” concrete sleepers.
– 702 Wooden sleepers.
– 482 Bridge and Crossing timbers.
– 11 sets of crossings.
– 1 set of switches.
– 29 rails.

Rather interestingly, this decision coinciding with the departure of their inventor.

Mr. Robert Baker, Manager and Chief Engineer, left the service on the 23rd March, retiring on pension with effect from 11th August. He was awarded the O.B.E. in June in recognition of his services to Government.

But despite their apparent “unsuitability”, according to page 16 of the 1948-49 annual report the concrete sleepers were still in main line service after decades of use:

Up to 31 March 1949 there were:

19,935 concrete sleepers on the Main Line
8,565 concrete sleepers on sidings
3 ,785 concrete sleepers lying in yard (not on track)

32,285 concrete sleepers against an approximate total of 35,000 manufactured between 1920 and 1934.

It is worthy of note that after an average period of 22 years, 90% of Baker’s concrete sleepers are still in existence. Unfortunately it was necessary, however, when replacing 85-lb. rails with 95-lb., to remove the concrete sleepers from the curves in the Main Line due to the wider bottom of the new rail and the insufficient spread allowed by the concrete sleepers. The concrete sleepers thus removed were re-used in other places.

This re-railing of the main line was eventually completed in February 1953, which I assume marked the end of these pioneering concrete sleepers on the Kowloon Canton Railway.

Footnote: concrete sleepers strike back

As part of the modernisation of the Kowloon Canton Railway through the 1970s, the line was relaid in even heavier rail – UIC54 profile at 54 kg/m, or 109-lb. in the old measures – laid on modern precast concrete sleepers.

Concrete sleepers on the East Rail line

Posted in Transport | Tagged , , , , , , , , | 1 Comment

Opening the third runway at Hong Kong International Airport

Hong Kong International Airport is currently being expanded with a third runway, with constructed started in 2016 and being completed in stages.


Airport Authority Hong Kong photo

In 2018 construction of the sea wall around the future northern runway commenced.

Silt curtains around the future site of the third runway

And in 2019 the first parcel of reclaimed land was handed over, allowing construction of the new North Runway to commence in 2020.

Hong Kong Airlines A320 takes off from Hong Kong

In December 2021 the existing North Runway was re-designated as the Centre Runway, to avoid conflicts with the new runway.

Airport Authority Hong Kong (AAHK) announced that the existing North Runway (07L/25R) at Hong Kong International Airport (HKIA) has been re-designated as the Centre Runway (07C/25C) today, signifying an important milestone for the expansion of the airport into a Three-runway System (3RS).

The new Third Runway, which will be put into operation in 2022, will be designated as the North Runway (07L/25R). Prior to that, the existing North Runway has to be re-designated as the Centre Runway (07C/25C) according to International Civil Aviation Organisation’s requirement.

At 0001hrs on 2 December, the North Runway of HKIA was closed to undergo the final re-designation procedures. The runway designation markings and the mandatory instruction markings of 07L and 25R on the runway and taxiways respectively were replaced by 07C and 25C.

Movement area guidance signs on the airfield, as well as relevant equipment and procedures for HKIA’s air traffic control and airport operations control systems were also modified. The South Runway remained in operation when the North Runway was being re-designated and air traffic movements at the HKIA operated smoothly throughout the period.

Existing runway signs had to be swapped out.


Airport Authority Hong Kong photo

Along with the identifiers painted on taxiways.


Airport Authority Hong Kong photo

And on the runway itself.


Airport Authority Hong Kong photo

In March 2022 a number of aircraft stands were also redesignated.


Airport Authority Hong Kong photo

To avoid conflicts with future taxiways.

Aircraft parking stand numbers at HKIA bear prefixes that indicate their location at the airport. The prefixes “C” and “E”, which were respectively used for cargo aircraft stands at the cargo apron and passenger stands at the east side of Terminal 1, will be employed as taxiway designators for the new taxiway system of 3RS, hence the re-designation of parking stands bearing the “C” and “E” prefixes.

The parking stands for passenger aircraft were closed overnight and those for cargo aircraft in phases, while ensuring normal aircraft operations during re-designation works. A total of 36 cargo aircraft stands were given the new prefix “X”, while nine passenger aircraft stands have adopted the prefix “N” or “S”, which follows their adjacent stands at Terminal 1. Relevant signage such as Movement Area Guidance Signs and Stand Number Indicators, as well as relevant systems, were also updated.

Operational familiarisation for flights on the new third runway commenced in July 2022.


Airport Authority Hong Kong photo

And on 25 November 2022 the third runway was officially commissioned.


Airport Authority Hong Kong photo

The airport configured as the Interim Two-Runway System (I-2RS) using the new North Runway and existing South Runway – the centre runway temporarily closed to be reconfigured for the new three runway layout. These works include levelling the runway pavement to tie in with connecting taxiways, constructing new runway entry and exit taxiways, and building new wrap-around taxiways at both ends of the runway.


Airport Authority Hong Kong photo

These works were completed ready for the first flight checks in August 2024, with the final three runway system opened to flights from 28 November 2024.


Airport Authority Hong Kong photo

Footnote: runway numbering

So what does 07L, 25R, 07C and 25C mean? 99% Invisible has the rundown on How to Decipher Two-Digit Airport Runway Designations, with Pilot Institute covering them in extra detail.

Posted in Transport | Tagged , , , , | Leave a comment

What is the MTR ‘Thank You Day’?

On my February 2024 visit to Hong Kong I noticed something odd one Saturday when travelling on the MTR – something called ‘Thank You Day’ when fares were half price. So why is a train operator expressing gratitude towards passengers?

Bank of ticket gates at Lok Fu station

The ‘Thank You Day’ page on the MTR website didn’t really give me a good answer.

50% Fare Discount on Thank You Day

To express our gratitude for your continuous support, passengers can enjoy 50% fare discount for every fare-paying trip using Octopus on the MTR, Light Rail and MTR Bus; or by QR code on the MTR heavy rail network on 24 February 2024.

Octopus: The offer is not applicable to First Class Premium on East Rail Line, Airport Express or MTR Feeder Bus. The offer can be used in conjunction with other fare promotions. Fare discount will be calculated separately. However, the total offer(s) The amount will not be higher than the fare paid for that trip. The fare discount will be rounded up to the next 10 cents.

And their ‘Thank You Day’ media release was more focused on the extra services they were running for the Spring Lantern Festival.

MTR to Launch Half-fare “Thank You Day” on 24 February 2024
8 February 2024

The MTR Corporation will hold a “Thank You Day” on 24 February 20242 (Saturday) to offer half- fare discount to thank passengers. Coinciding with the Spring Lantern Festival, about 370 train trips on various MTR lines will be added on that day to cater to additional patronage with the fare discount.

On 24 February, passengers can enjoy a 50% discount3 for every trip with their Octopus on the MTR, Light Rail and MTR Bus running in Northwest New Territories, or when they travel with a QR code on the heavy rail network. The half fare also applies to cross-boundary trips running to and from Lo Wu and Lok Ma Chau stations on the East Rail Line. Passengers can also enjoy the half fare together with any interchange discount, Fare Saver discount and the 25% discount on connecting journeys with Monthly Pass. The half-fare discount on “Thank You Day” is not applicable to MTR rides paid with contactless credit card or debit card.

Six MTR lines including the Island Line, South Island Line, Tsuen Wan Line, Kwun Tong Line, Tuen Ma Line and East Rail Line will run more frequent train trips than regular Saturdays on “Thank You Day” with a total of about 370 train trips added. For the Light Rail, more coupled-set Light Rail vehicles will be used to increase carrying capacity (please refer to Annex 1 for details of the train service enhancements). The Corporation will deploy extra staff at MTR stations to assist passengers and closely monitor train operations to suitably adjust train service and manpower arrangements when necessary.

“As the community celebrate the Spring Lantern Festival on 24 February, we hope the half fare and more frequent train trips will provide convenience to those who are out and about meeting up with families and friends,” said Ms Jeny Yeung, Managing Director – Hong Kong Transport Services of MTR Corporation.

Posters will be put up at different locations in the MTR network while the Corporation will provide information about the “Thank You Day” discount to passengers through various channels including MTR Mobile, MTR website and its official Facebook page.

But hidden in the footnotes was a short explanation of what ‘Thank You Day’ was.

According to the MTR Fare Adjustment Mechanism, once the Service Performance Rebate funding pool reaches the pre-defined amount, the MTR Corporation will arrange a “Thank You Day” on a specific Saturday or Sunday

So what is a Service Performance Rebate funding pool, and what is the pre-defined amount? Luckily Chinese-language Wikipedia goes into more detail on their “港鐵感謝日” (“MTR Thank You Day”) page.

“MTR Thank You Day” is a promotion offered by the MTR Corporation following changes to the Fare Adjustment Mechanism in 2023. Under the new mechanism, MTR will need to allocate corresponding amounts as discounts based on the company’s service performance.

If there is a delay of 31 minutes or more on a service operated by MTR Corporation, and the delay is caused by MTR Corporation’s operational process, MTR Corporation will be required to pay into the Service Performance Rebate funding pool for passengers. The amount paid is as follows:

Delay time Penalty
31–60 minutes $1 million
61–120 minutes $2 million
121–180 minutes $3 million
181–240 minutes $8 million
Every additional hour after 4 hours $4 million

During peak hours (8-9am and 6-7pm, Monday to Friday, the above penalty is increased by 20%), the maximum penalty for each incident is HK$40 million, which is a 12-hour delay.

For every HK$25 million accumulated in the “Service Performance Rebate” account in the previous year, one day must be designated as a “Thank You Day”.

In response to the MTR Corporation’s service performance in 2022, it is necessary to allocate $100 million for fare concessions. On March 21, 2023, MTR announced that it would offer discounts on April 8 and 9, and May 13 and 14 of the same year. As there was a balance left over from the four-day discount, another discount was offered on August 19.

Based on the MTR Corporation’s service performance in 2023, a fare concession of $25 million will be allocated. On February 8, 2024, MTR announced that it would launch a discount on February 24 of the same year.

So I suppose it’s less of a ‘Thank You’ and more of a ‘Please Forgive Our Delays’ day.

Waiting for a Kowloon bound Tsuen Wan line train at Admiralty station

Posted in Transport | Tagged , , , , , | Leave a comment

Preserved Hong Kong buses in the United Kingdom

I’ve written about Hong Kong double decker buses in Australia before, but it’s not the only place where retired Hong Kong buses are living a second life – a few have also ended up in the United Kingdom.

Kowloon Motor Bus MCW Metrobus Mk2

G899COY former KMB S3M249 MCW Metrobus MK2
Photo by km30192002 (CC BY 2.0)

The first is ex-Kowloon Motor Bus MCW Metrobus Mk2 double decker S3M249, originally registered EL7659 but now with UK registration G899COY.

Built back in May 1990, it was retired in May 2007, and was later purchased by a Mr. Tsui Ka-ho for preservation, but due to Hong Kong vehicle registration rules, it could not be used on public roads, and so was shipped to the UK in 2023.

Citybus Leyland Olympian

H493XNP former ET778 Citybus 152 Leyland Olympian with Alexander R-type Bodywork
Photo by km30192002 (CC BY 2.0)

And another is ex-Citybus Leyland Olympian double decker #152, originally registered ET778 but but now with UK registration H493XNP.

Delivered in January 1991, the downturn in traffic following the 2003 SARS epidemic saw a number of buses in the Citybus fleet sold to majority shareholder Stagecoach’s UK operation Megabus. However it never entered service with them, instead used as a parts donor. It was then sent for scrap, until it was purchased by UK bus collector Dave Rogers, who commenced restoration work on it in 2020, which was completed in 2023.

Citybus Volvo B10M/Van Hool Aizee

XIL8125 (Formerly J894CEV) Volvo B10M/Van Hool ALizee
Photo by Pete Edgeler (CC BY-NC-ND 2.0)

And finally ex-Citybus Volvo B10M/Van Hool Aizee coach #1273, originally registered FC9356 but but now with UK registration XIL8125.

New to Citybus in 1992, it was withdrawn from service in Hong Kong 2004 and purchased by a UK operator, where it continued in service until 2020, which it was purchased for preservation by Dave Rogers, and repainted into the original Citybus livery.

Further reading

Citybus Leyland Olympian double decker #152 also stared in the Netflix television series The Crown, for an episode covering the July 1997 handover of the then-British colony of Hong Kong to the People’s Republic of China.

Posted in Transport | Tagged , , , , , , , | Leave a comment